Crossing the streambed without permanent placement of materials or construction of structure
If fill material is placed, or would be discharged through grading, excavation, or dredging below the plane of the OHWM of the stream (even if it is temporary); or if dewatering and construction of a dam is required (even if it is temporary)
If alteration or modification of the bed, bank, or channel of a stream will occur, including excavation and grading work and removal of existing riparian vegetation